2009 |
Work completed July
- VFA Steering Committee maps strategy and charge for VFA Working Groups
- VFA Phase I planning culminates with the reports: Principles and Plans: A Voluntary Framework of Accountability and Performance Accountability Systems for Community Colleges: Lessons from Ten States
|
| September |
|
|
2010 |
| February |
- First Phase II Steering Committee meeting
|
| March |
- VFA Working Groups convene for inaugural working meetings
|
| March-July |
|
Development
- VFA Working Groups identify proposed measures; conceptualize data collection and display scheme and policy; and plan to convey need for VFA to the sector;
- VFA Steering Committee provides feedback and recommendations
- AACC VFA staff begins outreach on VFA through numerous presentations/forums
|
| July |
- AACC names a Technical Defi nitions Committee to convert proposed measures into working definitions for the VFA Draft Technical Manual v.1.0
|
| September |
- AACC begins work to develop VFA data tool specifications and wireframes
|
| November |
- AACC selects VFA Pilot Sites through a Request for Proposal process
|
| November- December |
- VFA Steering Committee and Working Groups perform review of proposed measures and draft technical manual
- VFA Draft Technical Manual v. 1.0 finalized
|
2011 |
| January |
- Formal announcement of VFA Pilot Sites and launch of pilot testing
|
| March |
- Pilot sites submit initial feedback on proposed measures and framework
|
| February-2011 |
- Development of framework and proposed measures continues (with plans to modify and add measures); AACC develops business model for the VFA
|
| April-2011 |
- Broad vetting of the measures and the prototypes of the data tool followed by modification of framework
|
2012 |